BDI is working with the City of Gulf Breeze to design two proposed methods of providing sanitary sewer to the Highpoint area. The project scope of work consists of surveying services to identify all improvements within the public rights-of-ways and the locations of existing septic tanks; preparation of construction contract documents, and assistance in obtaining regulatory approvals.
The first proposed method is the gravity sewer system of approximately 6,800 LF of 8” gravity sewer with 24-manholes, lift station, approximately 1,000 LF of force main, and conversion of up to 107 septic tanks to the gravity sewer system.
The second proposed method, the low-pressure system, will consist of approximately 2,800 LF of force main, valves and fittings, and conversion of up to 49-septic tanks with grinder pump stations connected to a low-pressure force main.